The original paper is in English. Non-English content has been machine-translated and may contain typographical errors or mistranslations. ex. Some numerals are expressed as "XNUMX".
Copyrights notice
The original paper is in English. Non-English content has been machine-translated and may contain typographical errors or mistranslations. Copyrights notice
Existem as três metas a seguir a serem alcançadas em um projeto de software a partir dos três pontos de vista de gerenciamento de processos (ou gerenciamento de progresso), gerenciamento de custos e gerenciamento de qualidade para que o projeto de software seja bem-sucedido: (a) elaborar um plano de desenvolvimento de software baseado em dados precisos. estimativa, (b) detecção precoce dos riscos que o projeto inclui com base na avaliação correta da situação, (c) prevenção precoce dos riscos que o projeto inclui. Neste artigo, os autores propõem um método e facilidades para projetar riscos em um projeto de software através do programa Kepner-Tregoe, e propõem o replanejamento do cronograma utilizando algoritmo genético para evitar os riscos projetados. Além disso, os autores mostram, a partir dos resultados de execução do sistema, que o sistema é eficaz em evitar precocemente os riscos que o projeto de software inclui.
The copyright of the original papers published on this site belongs to IEICE. Unauthorized use of the original or translated papers is prohibited. See IEICE Provisions on Copyright for details.
Copiar
Seiichi KOMIYA, Atsuo HAZEYAMA, "Projecting Risks in a Software Project through Kepner-Tregoe Program and Schedule Re-Planning for Avoiding the Risks" in IEICE TRANSACTIONS on Information,
vol. E83-D, no. 4, pp. 627-639, April 2000, doi: .
Abstract: There are the following three targets to be achieved in a software project from the three viewpoints of process management (or progress management), cost management, and quality management for software project to be successful: (a) drafting a software development plan based on accurate estimation, (b) early detection of risks that the project includes based on correct situation appraisal, (c) early avoidance of risks that the project includes. In this paper, the authors propose a method and facilities to project risks in a software project through Kepner-Tregoe program, and propose schedule re-planning by using genetic algorithm for avoiding the projected risks. Furthermore the authors show, from the results of execution of the system, that the system is effective in early avoidance of risks that the software project includes.
URL: https://global.ieice.org/en_transactions/information/10.1587/e83-d_4_627/_p
Copiar
@ARTICLE{e83-d_4_627,
author={Seiichi KOMIYA, Atsuo HAZEYAMA, },
journal={IEICE TRANSACTIONS on Information},
title={Projecting Risks in a Software Project through Kepner-Tregoe Program and Schedule Re-Planning for Avoiding the Risks},
year={2000},
volume={E83-D},
number={4},
pages={627-639},
abstract={There are the following three targets to be achieved in a software project from the three viewpoints of process management (or progress management), cost management, and quality management for software project to be successful: (a) drafting a software development plan based on accurate estimation, (b) early detection of risks that the project includes based on correct situation appraisal, (c) early avoidance of risks that the project includes. In this paper, the authors propose a method and facilities to project risks in a software project through Kepner-Tregoe program, and propose schedule re-planning by using genetic algorithm for avoiding the projected risks. Furthermore the authors show, from the results of execution of the system, that the system is effective in early avoidance of risks that the software project includes.},
keywords={},
doi={},
ISSN={},
month={April},}
Copiar
TY - JOUR
TI - Projecting Risks in a Software Project through Kepner-Tregoe Program and Schedule Re-Planning for Avoiding the Risks
T2 - IEICE TRANSACTIONS on Information
SP - 627
EP - 639
AU - Seiichi KOMIYA
AU - Atsuo HAZEYAMA
PY - 2000
DO -
JO - IEICE TRANSACTIONS on Information
SN -
VL - E83-D
IS - 4
JA - IEICE TRANSACTIONS on Information
Y1 - April 2000
AB - There are the following three targets to be achieved in a software project from the three viewpoints of process management (or progress management), cost management, and quality management for software project to be successful: (a) drafting a software development plan based on accurate estimation, (b) early detection of risks that the project includes based on correct situation appraisal, (c) early avoidance of risks that the project includes. In this paper, the authors propose a method and facilities to project risks in a software project through Kepner-Tregoe program, and propose schedule re-planning by using genetic algorithm for avoiding the projected risks. Furthermore the authors show, from the results of execution of the system, that the system is effective in early avoidance of risks that the software project includes.
ER -